plant room underway & mast is removed - june 2015

Work is well underway to the external grounds with foundations in for the new plant room.  We have also removed the mast to the main swimming pool.  You can see the moment it is taken down here.

BUILDING WORKS COMMENCE - APRIL 2015

We are delighted to announce that the diggers started on Monday 13th April. The first phase of the project is the building of the new plant room.  We will keep you posted with developments.

Successful funding applications - so far

We've got other funding applications underway and other initiatives in planning but here is an overview to where we currently stand with successful funding applications.

Heritage Lottery Funding - Enterprise Programme - £576,000 Development Funding & £4.2million Round Two

Coastal Communities Fund - £2.5million

Social Investment Business - £440,000

The People's Millions - £49,500

Social Investment Business - £61,330

And whilst its not grant funding, we have been awarded £330,000 Section 106 money from the Grand Ocean development in Saltdean towards the project.